In the Process Guidance for MSF Agile v100.1, in the workstream "Create a Scenario", activity "Prioritize Scenario List", sub-activity "Determine an Overall Priority" it says:
- Close the low priority scenarios that will be implemented in a future release using the deferred reason code.
What should I do Am I missing something
Thanks!
PD: By the way, in the MSF Agile Guidance v100.1 - "Create a Scenario" workstream, activity "Develop Lifestyle Snapshot" the link to the top level workstream points to "Create a Quality of Service Requirement" workstream. Shouldn't it point to "Create a Scenario" workstream

MSF Agile: cannot close scenarios
rchrismor013
Yes, unfortunately that's the only way to close them. We need a direct transition from active to closed, I know. We will have one in a future release.
Randy
MSF
Jim Evans
Active to Resolved
Resolved to Active
Resolved to Close
Close to Active.
One has to follow set of above mentioned states in order to close a scenario.In default process there is not transition from "Active" to "Close" directly.You may ofcourse customize it by modifying process templates and/or state transition rules.
Moreover "Resolve" state does not really say that a scenario has to be implemented in current iteration."Deferring" a scenario means that we may implement it in code but not in current iteration.